Lake Resources updates on the development at the Kachi project lithium processing demonstration plant

Nov 02, 2022

Lake Resources NL (ASX: LKE) has provided an update on development at the Kachi project lithium processing demonstration plant.

During September and October 2022, the Company was engaged in completing the construction of the demonstration plant on site and the wet and dry commissioning process. Currently, the demonstration plant is processing Kachi brines with final optimisation of the process now about to complete.

Bart Packer, the Vice President of Lilac Solutions was there at Kachi to supervise the final adjustments to the plant to confirm optimisation of processes before continual processing getting in progress.

David Snydacker, the Company’s CEO  said that after a month of the start of wet commissioning, the Company was able to achieve 80% lithium recoveries.

In the coming period, Third Party Validation will start shortly to allow DFS Completion.

 

 

Customer Notice:

Nextgen Global Services Pty Ltd trading as Kapitales Research (ABN 89 652 632 561) is a Corporate Authorised Representative (CAR No. 1293674) of Enva Australia Pty Ltd (AFSL 424494). The information contained in this website is general information only. Any advice is general advice only. No consideration has been given or will be given to the individual investment objectives, financial situation or needs of any particular person. The decision to invest or trade and the method selected is a personal decision and involves an inherent level of risk, and you must undertake your own investigations and obtain your own advice regarding the suitability of this product for your circumstances. Please be aware that all trading activity is subject to both profit & loss and may not be suitable for you. The past performance of this product is not and should not be taken as an indication of future performance.